CCS Commercial / Project record

Island’s Pancake House

Completed walk-in exterior in kitchen.

Completed / Big Pine Key, Florida

Walk-in cooler replacement

Project start: August 9, 2026 · Completion and startup: August 22, 2026

CCS completed the demolition, relocation, replacement, and commissioning of the walk-in cooler serving Island’s Pancake House.

The challenge

Make the installation fit the facility.

Field layout identified a height conflict at the original cooler location. Installation paused before panels were modified, and an owner-approved kitchen location was selected for the replacement enclosure.

The scope

From demolition through commissioning.

Work included removal of the original equipment and enclosure; layout, leveling, continuous base support, and sealing; installation of the AmeriKooler enclosure, BOHN IntelliGen evaporator, and Heatcraft remote condenser; refrigeration piping; controls; and startup checks.

The result

Complete and operational.

The replacement system was commissioned on August 22, 2026. The project report recorded a 36.5°F box temperature during final checks and approximately 38°F at the door display after pull-down. A factory control connection fault identified during startup was corrected before closeout.

Photo record / 01

Existing conditions

Photo record / 02

Envelope and access conditions

Photo record / 03

Demolition

Photo record / 04

Relocation planning

Photo record / 05

Kitchen preparation

Photo record / 06

Base support and leveling

Photo record / 07

Enclosure assembly

Photo record / 08

Remote condenser installation

Photo record / 09

Equipment and controls

Photo record / 10

Piping and commissioning

Photo record / 11

Operating checks

Photo record / 12

Completed installation

Photo source: CCS Island Pancake House Walk-In Cooler Completion Report, August 2026. Captions describe the documented work sequence.